A stone threshing barn becoming a four-bedroom home. We update this page after every site visit, so you can see what is done, what is happening now and when we next need you on site.
Overall progress
58%
Handover on 26 February 2027 is on schedule.
Done · 12 Jan 2026
Survey and consents
Measured survey, bat survey and listed building consent granted.
Done · 23 Mar 2026
Strip out and groundworks
Concrete floor broken out, new drains and a limecrete slab.
Done · 29 Jun 2026
Frame repairs
Oak frame repaired in place, with eleven new rafters.
IN PROGRESS
Roof and envelope
3 Aug to 17 Oct 2026
Reclaimed stone slates are back on the south slope and the north slope is 70% done.
From 20 Oct 2026
First fix and insulation
Wiring, plumbing and wood fibre insulation between the rafters.
Keys on 26 Feb 2027
Finishes and handover
Lime plaster, joinery, the kitchen and a final walk round together.
LATEST FROM SITE
Friday 18 September
The scaffold is up on the north slope and most of the slates are back. We found beetle damage in two more rafters and replaced them like for like. It cost us two days, but the roof will still be finished by 17 October and the handover date does not move.